State of data center hiring

Every number on this page comes from one of our studies, and every study comes from the 109 projects in our nine market trackers plus public records we read ourselves: BLS, the Department of Labor, each company's careers site and each project's own filings. The studies are linked where the numbers come from, and each one updates monthly.

Czarina Tabayoyong, founder of Critical Path Hiring

By Czarina Tabayoyong, Founder, Critical Path Hiring. Former Amazon, AWS and Google recruiter.

Last reviewed · First published · Next update

Recomputed with every study refresh.

Refresh alerts

One email each time this page is refreshed, with what changed.

Privacy policy

The numbers

109
projects tracked in nine markets. Source
5,204 MW
stated capacity under construction. Source
10,008 to 27,755
construction workers that capacity needs at peak, estimate. Source
31 of 109
projects stalled, denied or withdrawn. Source
3,325 MW
stated capacity on blocked projects, 2,951 of it stalled rather than cancelled. Source
7
sites in their commissioning window this quarter, in 6 markets, plus 6 year-only targets. Source
21.5 months
median from public approval to first stated completion. Source
12 months
median from groundbreaking to first capacity. Source
18 of 23
sites under construction held by established operators. Source
17 of 37
projects from funds, landowners and first-time developers that were blocked. Source
2,314
open hyperscaler data center roles, 66% of them Amazon. Source
68 of 109
projects that state no permanent job figure. Source

The hiring chain

Read left to right, this is what the studies say happens to a tracked project and who gets hired when.

  1. 01

    Approval

    A council, commission or county vote. In Texas it usually comes late, as a tax abatement after design; in Illinois it comes first. Median 21.5 months from here to first capacity.

    Study
  2. 02

    Groundbreaking

    About 10 months after the vote on a typical tracked project. Construction hiring starts: an estimated 1.9 to 5.3 workers per MW at peak, drawn from a metro pool that in San Antonio and Columbus is small relative to the demand.

    Study
  3. 03

    Peak construction

    For every permanent job promised, about 16.1 construction jobs are stated by the projects that state both. Most of the workforce a site ever employs is on it now.

    Study
  4. 04

    Commissioning window

    The last two quarters before completion, about 6 months after groundbreaking. 7 tracked sites are in it this quarter. Commissioning agents and engineers are mostly hired through firms; only Amazon and Oracle post them under their own names.

    Study
  5. 05

    Turnover

    Construction and commissioning crews leave for the next site. The permanent operations team, a median of about 39 jobs per 100 MW where stated, stays. 68 of 109 projects never state that figure.

    Study

Market scorecard

One row per tracked market, with each study's figure for that market. Hyperscaler roles are counted by state, so the two Texas markets share a figure.

  • Under construction
  • Blocked
Stated MW under construction against stated MW on blocked projects, by marketNorthern Virginia: 1000 MW under construction, 0 MW blocked; Dallas-Fort Worth: 370 MW under construction, 48 MW blocked; Phoenix: 497 MW under construction, 0 MW blocked; Atlanta: 354 MW under construction, 651 MW blocked; Columbus: 1000 MW under construction, 200 MW blocked; Salt Lake City: 175 MW under construction, 530 MW blocked; San Antonio: 1700 MW under construction, 0 MW blocked; Hillsboro: 108 MW under construction, 10 MW blocked; Chicago: 0 MW under construction, 1886 MW blocked0 MW500 MW1,000 MW1,500 MWChicago: Under construction 0, Blocked 1,886Chicago1,886 MWSan Antonio: Under construction 1,700, Blocked 0San Antonio1,700 MWColumbus: Under construction 1,000, Blocked 200Columbus1,200 MWAtlanta: Under construction 354, Blocked 651Atlanta1,005 MWNorthern Virginia: Under construction 1,000, Blocked 0Northern Virginia1,000 MWSalt Lake City: Under construction 175, Blocked 530Salt Lake City705 MWPhoenix: Under construction 497, Blocked 0Phoenix497 MWDallas-Fort Worth: Under construction 370, Blocked 48Dallas-Fort Worth418 MWHillsboro: Under construction 108, Blocked 10Hillsboro118 MW
Stated capacity only. Chicago's one site under construction states no MW; its 1,886 MW blocked is mostly the Joliet Technology Center, held up in court.
MarketProjectsUnder constructionBlockedMW under constructionPeak demand, share of metro construction workforceMW blockedSites in Cx window nowNo job figureOpen hyperscaler roles, state
Northern Virginia1012 of 101,0001.7% to 4.7%113,410 employednot stated6 of 1046312 commissioning
Dallas-Fort Worth1443 of 143702 with no MW0.4% to 1.2%162,920 employed48112 of 1441527 commissioning
Phoenix1424 of 144970.7% to 2.0%132,260 employednot stated19 of 14685 commissioning
Atlanta1425 of 143540.7% to 2.0%93,260 employed6519 of 1413013 commissioning
Columbus1454 of 141,0004 with no MW4.9% to 14%39,220 employed20015 of 141434 commissioning
Salt Lake City1132 of 111752 with no MW0.7% to 2.0%46,030 employed53014 of 11151 commissioning
San Antonio1132 of 111,7007.2% to 20%45,550 employednot stated27 of 1141527 commissioning
Hillsboro923 of 91081 with no MW0.4% to 1.0%57,870 employed107 of 92311 commissioning
Chicago1216 of 12not stated1 with no MW132,250 employed1,88619 of 12311 commissioning

Commissioning

Pay

Median posted ranges from 48 public postings: commissioning engineers $101K to $159K a year (16 postings), commissioning agents $84K to $140K (5), commissioning technicians $38 to $60 an hour (5). Pay ranges

Credentials

17 of 46 postings name a commissioning certification and 2 require one. A PE license is named more often than any commissioning certification, in 14 of 46. Certifications

Who hires

24 employers had a live data center commissioning posting this fall, 8 of them commissioning, testing and engineering firms. Among the hyperscalers, 77 open commissioning roles, all at Amazon and Oracle. Employers

Timing

7 tracked sites are in their commissioning window this quarter across 6 markets, the peak quarter in the set. 2027 holds four to five every quarter. Windows by market

Questions

Where is data center construction labor tightest right now?
San Antonio and Columbus. On stated capacity under construction, San Antonio's sites need an estimated 7.2% to 20% of the metro's construction workforce at peak and Columbus's 4.9% to 14%. Northern Virginia absorbs a build of the same size at 1.7% to 4.7%.
How long does a data center owner have to hire after approval?
About 21.5 months from the approving vote to the first stated completion on the projects we track, and about 12 months from groundbreaking. The commissioning window is the last two quarters before completion, so commissioning hiring starts roughly 6 months after groundbreaking.
What do data center commissioning jobs pay?
Median posted ranges in our October 2026 set of 48 postings: commissioning engineers $101K to $159K a year (16 postings), commissioning agents $84K to $140K (5), commissioning technicians $38 to $60 an hour (5). 17 of 46 postings name a commissioning certification and 2 require one.

Hiring call

Book a hiring call and we'll talk through which roles your build needs and when to bring them on.

Czarina Tabayoyong, founder of Critical Path Hiring

Czarina Tabayoyong

Founder and principal recruiter, Critical Path Hiring. Czarina recruits commissioning, MEP, power and critical facilities people for data center builds. She previously recruited cloud and data center architecture talent at AWS Professional Services, and PMO and project delivery talent for hyperscale data center campuses in Texas and Virginia.