Salt Lake City data center project tracker

Data center projects in the Salt Lake City area and nearby Utah counties that are proposed, approved, under construction, stalled or cancelled. Each row links to the public record or news report its stage comes from. Last checked October 23, 2026.

By Czarina Tabayoyong, Founder, Critical Path Hiring

Last reviewed · First published · Next update

Reviewed as projects move between stages.

Refresh alerts

One email each time this page is refreshed, with what changed.

Privacy policy

Projects

Showing 11 of 11 projects

Salt Lake City data center projects by stage, with sources
ProjectDeveloperCountySize reportedStageLatest statusSource
QTS Eagle Mountain campus (SLC1)QTS Data CentersUtah (Eagle Mountain)Not statedUnder constructionWork began September 2025; official groundbreaking October 2025; third building topped out April 2026utahbusiness.com
Novva West Jordan campusNovva Data Centers and CIM GroupSalt Lake (West Jordan)100 acres; 1.5 million sq ft planned; 175 MW at completionUnder constructionPhase 1 operating since 2023; phases 2 and 3 under construction and expected to finish in 2026, reported March 2025constructconnect.com
Joule AI data center and energy campusJoule Capital PartnersMillardAbout 4,000 acresUnder constructionMillard County commission approved project August 2025; groundbreaking November 2025; power expected to begin in 2026abc4.com
Stratos ProjectNot named in the cited report; Kevin O'Leary is backing itBox Elder (unincorporated)About 20,000 acres, per county officials; MW not statedApprovedCounty commissioners approved interlocal agreement giving land-use authority to MIDA for 50 years May 2026; county 180-day moratorium on new data centers passed June 2026 excludes Stratos; referendum lawsuits filed in 1st District Court June 2026upr.org
Nebo North data center campusNebo North LLCJuab (Mona)361 acres; up to 10 buildings of about 300,000 sq ft each; $10 billion estimatedApprovedPlanning commission approved conditional use permit April 2026; site plan not yet submitted as of early September 2026; residents filed appeal September 2026 asking county to overturn permit and halt project worksltrib.com
Creekstone Energy data center campusCreekstone EnergyMillard$17 billion investment; MW and acres not statedApprovedPlans announced April 2026; Utah Governor's Office of Economic Opportunity awarded rural tax increment financing incentive; no construction reportedareadevelopment.com
Tract Eagle Mountain landTractUtah (Eagle Mountain)More than 668 acres; more than 400 MW of new transmission plannedApprovedLand purchase completed January 2024; site is in an overlay allowing data centers by right; power delivery targeted for 2028utahbusiness.com
Meta Eagle Mountain expansionMetaUtah (Eagle Mountain)Not stated for new buildings; total Utah investment more than $3 billionProposedFourth campus expansion announced September 2026; full details not released; closed-loop liquid cooling planneddatacenterdynamics.com
Volition data centerVolitionUtah (Spanish Fork)440,000 sq ft warehouse; original proposal 225 MWProposedCity council amended zoning to allow original proposal September 2026; Volition agreed to move to Stockman Flats warehouse site September 2026; site plan, studies and development agreement still requiredsltrib.com
Tooele Valley Project Area data centerLocal developer named in the cited reportTooele (near I-80 and Burmester Road)500 MW on about 200 acresStalledCounty council directed staff to draft data center rules June 2026; county has not approved plans; state water discharge permit hearing held July 2026 with no decisionsltrib.com
B+F Timpanogos Tech data centerB+F Timpanogos TechUtah (Provo)66,000 sq ft; about 5 MW initial, up to 30 MW; about $280 millionCancelledCity council voted unanimously to deny the rezoning March 2026, against city staff's recommendation; developer may reapplydatacenterdynamics.com

Hiring by stage

Each project's stage comes from its latest source. The hiring column shows who employers usually hire at that stage.

Hiring by project stage
StageHiring
Under constructionElectricians, superintendents and MEP coordinators, plus commissioning teams as buildings near completion
ApprovedPreconstruction and design roles first, then construction crews once power dates firm up
ProposedNo hiring yet
Stalled or cancelledNone

See the Salt Lake City market page and the hiring timeline by build stage. We also track projects in Northern Virginia, Dallas-Fort Worth, Phoenix, Chicago, Hillsboro, Oregon, San Antonio, Columbus and Atlanta. Totals for every market are on the U.S. data center project tracker.