Hillsboro, Oregon data center project tracker

Data center projects in Hillsboro and nearby Oregon counties that are proposed, approved, under construction, stalled or cancelled. Each row links to the public record or news report its stage comes from. Last checked October 23, 2026.

By Czarina Tabayoyong, Founder, Critical Path Hiring

Last reviewed · First published · Next update

Reviewed as projects move between stages.

Refresh alerts

One email each time this page is refreshed, with what changed.

Privacy policy

Projects

Showing 9 of 9 projects

Hillsboro, Oregon data center projects by stage, with sources
ProjectDeveloperCountySize reportedStageLatest statusSource
Aligned Hillsboro PDX-01 and PDX-02Aligned Data CentersWashington (Hillsboro)72 MW for PDX-01 on a 27-acre site; PDX-02 planned at 36 MWUnder constructionGroundbreaking October 2023; PDX-01 topped out July 2024; PDX-02 planned to followdatacenterdynamics.com
Google The Dalles campus expansionGoogleWasco (The Dalles)Not statedUnder constructionFourth building completed 2025; another building planned to finish in 2026opb.org
Flexential Hillsboro 6FlexentialWashington (Hillsboro)350,000 sq ft, 27 MWApprovedLand parcel acquired; announced September 2025; construction start not statedbaxtel.com
Stack Hillsboro campus expansion (POR03)Stack InfrastructureWashington (Hillsboro)121 MW expansion; campus to reach 200 MWApprovedExpansion first announced July 2022; first phase POR03D (25 MW) due Q4 2027 per February 2026 report; construction not reported in this sourcedatacenterdynamics.com
Wagon Data CenterDigital RealtyWashington (Hillsboro)About 15.7 acres, roughly 496,540 sq ftProposedLand use application filed July 2026, before the city's 120-day moratorium; site about 200 feet from Liberty High Schoolkatu.com
Corny Data CenterNot named in the cited reportWashington (Hillsboro)Nearly 29 acresProposedNew data center application filed July 2026 with a 10% height adjustment request; continuing review under pre-moratorium rulesyouroregonnews.com
Oakline at Mill Creek (Salem)Verrus, backed by Sidewalk Infrastructure PartnersMarion (Salem)75-acre site; two buildings, 600,000 sq ft combined footprintStalledGovernor blocked sale of 32 acres of state land; Verrus filed a Phase 1 site plan without that land; Salem adopted a four-month data center moratorium September 2026, running to January 2027kptv.com
Aligned new Hillsboro data center near NE 30th AvenueAligned Data CentersWashington (Hillsboro)Not statedStalledPreapplication conference requested July 2026 after Stack filed; not a land use application so it cannot be processed until the Hillsboro moratorium is liftedyouroregonnews.com
Cascade Locks Flex Building Six data centerRoundhouse Digital InfrastructureHood River (Cascade Locks)10 MW proposed; first building about 44,000 sq ftCancelledAnnounced March 2023; Cascade Locks Port Authority and developer ended the project July 2023 after resident and mayor oppositiondatacenterdynamics.com

Hiring by stage

Each project's stage comes from its latest source. The hiring column shows who employers usually hire at that stage.

Hiring by project stage
StageHiring
Under constructionElectricians, superintendents and MEP coordinators, plus commissioning teams as buildings near completion
ApprovedPreconstruction and design roles first, then construction crews once power dates firm up
ProposedNo hiring yet
Stalled or cancelledNone

See the Hillsboro, Oregon market page and the hiring timeline by build stage. We also track projects in Northern Virginia, Dallas-Fort Worth, Phoenix, Chicago, San Antonio, Salt Lake City, Columbus and Atlanta. Totals for every market are on the U.S. data center project tracker.