Data center tracker

Atlanta data center project tracker

Data center projects in metro Atlanta and nearby Georgia counties that are proposed, approved, under construction, stalled or cancelled. Each row links to the public record or news report its stage comes from. Last checked October 23, 2026.

By Czarina Tabayoyong, Founder, Critical Path Hiring

Last reviewed · First published · Next update

Reviewed as projects move between stages.

Refresh alerts

One email each time this page is refreshed, with what changed.

Privacy policy

Projects

Showing 14 of 14 projects

Atlanta data center projects by stage, with sources
ProjectDeveloperCountySize reportedStageLatest statusSource
DC BLOX Atlanta West Hyperscale CampusDC BLOXDouglas (Lithia Springs)About 1.25 million sq ft on 54 acres; 200 MW critical load designedUnder constructionUnder construction with phased delivery through 2027, reported August 2025; $1.15 billion green loan securedcommercialsearch.com
DC BLOX Atlanta East Hyperscale CampusDC BLOXRockdale (Conyers)747,787 sq ft on 68 acres; 154 critical MW committed and plannedUnder constructionDC BLOX reports construction under way; site preparation began September 2024dcblox.com
Wallace Jackson Data Center CampusWallace Jackson LLCSpalding (near Griffin)Nearly 5 million sq ft, 10 buildings on about 190 acres; $3.9 billionApprovedCounty commissioners unanimously approved three zoning requests January 2026; filing projects full build-out by 2035; no construction reporteddatacenterdynamics.com
Rumble Technology ParkCloverleaf InfrastructureMonroe (near Forsyth)1.12 GW at full buildout; 12 buildings, 4.2 million sq ft; over 1,200 acres with expansionApprovedOriginal 525-acre rezoning approved November 2024; 300-acre expansion proposed August 2025, with county votes set for September 2025newprojectmedia.com
Social Circle data center siteNot statedWalton (Social Circle)Not statedApprovedCity council voted 2 to 1 to rezone the land for a data center November 2025; planning commission had recommended denial; no construction reportedatlantanewsfirst.com
Microsoft Project Firecracker campusMicrosoftFloyd (Rome)Three buildings up to 1,659,000 sq ft on 349 acres; 422 MWProposedDevelopment of Regional Impact application filed October 2026 for 0 Huffaker Road; estimated completion 2032datacenterdynamics.com
Microsoft ATL50MicrosoftFulton (Union City)Two buildings totaling 910,000 sq ft on 88 acresProposedDevelopment of Regional Impact application filed September 2026; site set to launch in 2032datacenterdynamics.com
DataBank Cartersville campusDataBankBartow (Cartersville)200 MW on 69 acres; 1.1 million sq ftProposedDevelopment of Regional Impact application and 288 MW grid connection request filed June 2026; first phase could launch in 2032datacenterdynamics.com
QTS ATL2 East (Fayetteville expansion)QTSFayette (Fayetteville)2 million sq ft on about 313 acresProposedDevelopment of Regional Impact application filed January 2026 by QTS Eastwood LLC; could be completed by 2029datacenterdynamics.com
Project SailAtlas DevelopmentCoweta (near Newnan)Almost 830 acres; $17 billion expected costStalledCommissioners approved rezoning 3 to 2 April 2026; 19 residents sued the county and Atlas May 2026 to prevent or delay work; construction start not reportedwsbtv.com
Shadowbox Studios data centerShadowbox Studios (Henrico 183 LLC)DeKalb (International Park Drive)651 MW requested from Georgia Power; 166 acresStalledZoning Board of Appeals blocked the plan; studio sued the county seeking $30 million, reported October 2026; county moratorium extended through March 2027hoodline.com
Liberty Road data center campusEdgeConnex (applicant East Dothan Village)Douglas (near Villa Rica)Six buildings, 4.4 million sq ft on 700 acres, about 130 acres for the campusCancelledCommission voted 4 to 1 to deny the rezoning, land use amendment and special use permit July 2026, the second denial in seven monthstimes-georgian.com
Stillwater Technology ParkNot statedClayton (Lovejoy)15 buildings on 403 acresCancelledDevelopers withdrew plans after resident opposition; city council formally accepted the withdrawal August 2026; city to revise zoning to exclude data centerswabe.org
Highway 85 North data centerCrow Holdings Development and CHI/AcquisitionsFayette (Fayetteville)About 300,000 sq ft on 37.4 acres; one building and a substationCancelledPlanning and zoning commission rejected the site plan January 2026; developer withdrew its appeal March 2026, ending the applicationdatacenterdynamics.com

Hiring by stage

Each project's stage comes from its latest source. The hiring column shows who employers usually hire at that stage.

Hiring by project stage
StageHiring
Under constructionElectricians, superintendents and MEP coordinators, plus commissioning teams as buildings near completion
ApprovedPreconstruction and design roles first, then construction crews once power dates firm up
ProposedNo hiring yet
Stalled or cancelledNone

See the Atlanta market page and the hiring timeline by build stage. We also track projects in Northern Virginia, Dallas-Fort Worth, Phoenix, Chicago, Hillsboro, Oregon, San Antonio, Salt Lake City and Columbus. Totals for every market are on the U.S. data center project tracker.