Chicago data center project tracker

Data center projects in the Chicago area and nearby Illinois counties that are proposed, approved, under construction, stalled or cancelled. Each row links to the public record or news report its stage comes from. Last checked October 23, 2026.

By Czarina Tabayoyong, Founder, Critical Path Hiring

Last reviewed · First published · Next update

Reviewed as projects move between stages.

Refresh alerts

One email each time this page is refreshed, with what changed.

Privacy policy

Projects

Showing 12 of 12 projects

Chicago data center projects by stage, with sources
ProjectDeveloperCountySize reportedStageLatest statusSource
T5 Chicago IV (Cornerstone business park)T5 Data CentersLake (Grayslake)472 acres; up to 18 buildings, about 10.1 million sq ft; first building about 800,000 sq ft; expected $18 billion investmentUnder constructionVillage approvals granted September 2024 to May 2025; building permit for the first building issued September 2026; opponents' lawsuit pendingdailyherald.com
Project CardinalPioneerKendall (Yorkville)1,000 acresApprovedCity council gave final approval to annexation, development and utility agreements and rezoning in March 2026; one no vote; approval clears the way for the developer to close on the land and begin constructionwspynews.com
Project VectorEdged (Endeavour Energy)DeKalb (DeKalb)About 560 acres; four data center buildings and two substations; megawatts not statedApprovedCity council unanimously approved the project in December 2025; incentives include a county enterprise zone property tax abatement, a state enterprise zone benefit and a city electricity tax incentiveshawlocal.com
Equinix Minooka campusEquinixMinooka (county not stated in source)About 300 acres; seven buildings; $6 billionApprovedAnnounced April 2026; report says construction starts in 2027; partial opening targeted 2028 and full opening 2031shawlocal.com
Batavia data center (1780 Hubbard Ave.)Hut 8 Corp. (through Batavia DC Corp.)Kane (Batavia)50 MW; about 120,000 sq ft; about $500 millionProposedCity council approved an electricity agreement 12 to 1 in July 2025; water agreement and design review still neededdailyherald.com
Beverly Road and Route 72 parcel (Plote property)Plote PropertiesKane (East Dundee)74 acres, part of a 253-acre Plote property; megawatts not statedProposedAnnexation talks in August 2026 included a data center as a possible future use; no immediate construction plansdailyherald.com
Joliet Technology CenterPowerHouse Hillwood Holding (PowerHouse Data Centers and Hillwood)Will (Joliet)795 acres; 24 buildings; 1.8 GW; about $20 billionStalledCity council approved annexation 8 to 1 in March 2026; resident group filed suit in May 2026 asking the court to void the approval; no ruling reported; first sub-campus slated for completion in 2028shawlocal.com
Naperville data center (Naperville and Warrenville roads)Karis CriticalDuPage (Naperville)145,000 sq ft; 36 MWCancelledCity council rejected the proposal 6 to 1 in January 2026; developer said it is assessing options and evaluating other sites in the regionbisnow.com
Barrington Hills data center (Penny Road)Brennan Investment GroupBarrington Hills (county not stated in source)$2 billion investment; megawatts and square footage not statedCancelledDeveloper withdrew its application after local opposition in February 2026; planned February 2 plan commission presentation cancelled; village considers the matter closeddatacenterdynamics.com
Lisle data center (711 Ogden Ave.)Cloud Centers LLCDuPage (Lisle)256,000 sq ft; 50 MWCancelledPublic meeting postponed in January 2026 after crowd exceeded room capacity; developer withdrew its application in March 2026; village exploring other redevelopment options for the sitepatch.com
Project Kilo (Kenyon Road and Route 25)White Rose PartnersKane (South Elgin)200,000 sq ft on 20 acresCancelledVillage board unanimously approved a resolution stating intent to deny annexation for a data center and voted down the special use permit in August 2026; developer said all options are on the table, including a possible lawsuitdailyherald.com
Meyer property data center (near Caledonia subdivision)Not named in the cited reportKendall (Yorkville)Not statedCancelledCity council tabled the rezoning in March 2026; developer withdrew the petition in April 2026 after talks showed insufficient council supportwspynews.com

Hiring by stage

Each project's stage comes from its latest source. The hiring column shows who employers usually hire at that stage.

Hiring by project stage
StageHiring
Under constructionElectricians, superintendents and MEP coordinators, plus commissioning teams as buildings near completion
ApprovedPreconstruction and design roles first, then construction crews once power dates firm up
ProposedNo hiring yet
Stalled or cancelledNone

See the Chicago market page and the hiring timeline by build stage. We also track projects in Northern Virginia, Dallas-Fort Worth, Phoenix, Hillsboro, Oregon, San Antonio, Salt Lake City, Columbus and Atlanta. Totals for every market are on the U.S. data center project tracker.