October 2026 study
Blocked data center capacity and construction jobs
Our pushback study counts 31 tracked projects stalled, denied or withdrawn. This page adds up what those projects stated about their size and converts the stated capacity into the construction workforce it would have needed. 9 of the 31 state a capacity: 3,325 MW, or an estimated 6,395 to 17,734 construction workers at peak.
By Czarina Tabayoyong, Founder, Critical Path Hiring. Former Amazon, AWS and Google recruiter.
Last reviewed · First published · Next update
Updated with the monthly tracker refresh.
Refresh alerts
One email each time this page is refreshed, with what changed.
Findings
- 3 stalled projects (Shadowbox Studios data center, Tooele Valley Project Area data center, Joliet Technology Center) hold 2,951 of the 3,325 stated MW. The 6 cancelled projects that state a figure add up to 374 MW.
- Joliet Technology Center alone is 1,800 MW, held up in court since May 2026. At peak it would need an estimated 3,462 to 9,600 workers, 2.6% to 7.3% of the 132,250 construction workers in the Chicago metro. No Chicago project under construction states a capacity, so this blocked site is the largest stated demand in the market.
- Illinois accounts for 1,886 of the 3,325 stated MW across three blocked projects. Georgia is next with Shadowbox Studios' 651 MW request to Georgia Power, frozen by a county moratorium.
- Council and board denials stopped the most projects (10 of 31) but little stated capacity: 314 MW. Court cases and utility boards stopped fewer projects and far more MW.
- 13 of the 31 state a square footage, 36,485,800 sq ft combined. 7 state an investment, $56.8 billion combined. 10 state no size figure of any kind.
By state
- Stalled
- Cancelled
Blocked projects with a stated MW. Peak workers are estimates at 1.9 to 5.3 per MW.
| State | Blocked projects with MW | Stated MW | Peak workers, estimate | Stalled MW | Cancelled MW |
|---|---|---|---|---|---|
| Illinois | 3 of 6 | 1,886 | 3,627 to 10,059 | 1,800 | 86 |
| Georgia | 1 of 5 | 651 | 1,252 to 3,472 | 651 | 0 |
| Utah | 2 of 2 | 530 | 1,020 to 2,827 | 500 | 30 |
| Ohio | 1 of 4 | 200 | 385 to 1,067 | 0 | 200 |
| Texas | 1 of 5 | 48 | 92 to 256 | 0 | 48 |
| Oregon | 1 of 3 | 10 | 19 to 53 | 0 | 10 |
| All nine markets | 9 of 31 | 3,325 | 6,395 to 17,734 | 2,951 | 374 |
Virginia's two blocked projects, including the 23 million sq ft Prince William Digital Gateway, state no MW, so Virginia shows no row. Arizona's four state none either.
Stop method
| Stopped by | Projects | With a stated MW | Stated MW | Peak workers, estimate |
|---|---|---|---|---|
| Council or board denial | 10 | 4 | 314 | 604 to 1,675 |
| Developer withdrawal | 8 | 2 | 60 | 115 to 320 |
| Moratorium | 5 | 1 | 651 | 1,252 to 3,472 |
| Court | 4 | 1 | 1,800 | 3,462 to 9,600 |
| Utility or water board | 2 | 1 | 500 | 962 to 2,667 |
| Planning commission | 1 | 0 | ||
| Referendum | 1 | 0 |
Project sizes
| Project | Market | Stage | Stopped by | Stated MW | Sq ft | Investment | Peak workers, estimate |
|---|---|---|---|---|---|---|---|
| Joliet Technology Center | Chicago | Stalled | Court, May 2026 | 1,800 | $20 billion | 3,462 to 9,600 | |
| Shadowbox Studios data centerRequested from Georgia Power | Atlanta | Stalled | Moratorium, July 2025 onward | 651 | 1,252 to 3,472 | ||
| Tooele Valley Project Area data center | Salt Lake City | Stalled | Utility or water board, July 2026 | 500 | 962 to 2,667 | ||
| Aligned Pataskala data center | Columbus | Cancelled | Council or board denial, August 2026 | 200 | 385 to 1,067 | ||
| Lisle data center (711 Ogden Ave.) | Chicago | Cancelled | Developer withdrawal, March 2026 | 50 | 256,000 | 96 to 267 | |
| Long Creek Road data center | Dallas-Fort Worth | Cancelled | Council or board denial, March 2026 | 48 | 202,800 | 92 to 256 | |
| Naperville data center (Naperville and Warrenville roads) | Chicago | Cancelled | Council or board denial, January 2026 | 36 | 145,000 | 69 to 192 | |
| B+F Timpanogos Tech data centerAbout 5 MW initial, up to 30 MW | Salt Lake City | Cancelled | Council or board denial, March 2026 | 30 | 66,000 | $0.3 billion | 58 to 160 |
| Cascade Locks Flex Building Six data center | Hillsboro | Cancelled | Developer withdrawal, July 2023 | 10 | 44,000 | 19 to 53 | |
| Prince William Digital Gateway | Northern Virginia | Cancelled | Court, July 2026 | 23,000,000 | |||
| Tract Yuma and Perryville Roads rezoning request | Phoenix | Cancelled | Developer withdrawal, April 2024 | 5,600,000 | $14 billion | ||
| Liberty Road data center campus | Atlanta | Cancelled | Council or board denial, July 2026 | 4,400,000 | |||
| Project Midway | Phoenix | Stalled | Planning commission, July 2026 | 1,250,000 | |||
| Oakline at Mill Creek (Salem) | Hillsboro | Stalled | Moratorium, September 2026 | 600,000 | |||
| Chandler AI data center and business complex | Phoenix | Cancelled | Council or board denial, December 2025 | 422,000 | |||
| Highway 85 North data center | Atlanta | Cancelled | Developer withdrawal, March 2026 | 300,000 | |||
| Project Kilo (Kenyon Road and Route 25) | Chicago | Cancelled | Council or board denial, August 2026 | 200,000 | |||
| Project Sail | Atlanta | Stalled | Court, May 2026 | $17 billion | |||
| AWS Sunbury Business and Technology Park campus | Columbus | Stalled | Moratorium, April 2026 | $2 billion | |||
| Francis Harris Lane data center | San Antonio | Cancelled | Council or board denial, February 2026 | $1.5 billion | |||
| Barrington Hills data center (Penny Road) | Chicago | Cancelled | Developer withdrawal, February 2026 | $2 billion |
The 10 blocked projects with no stated MW, square footage or investment are listed on the pushback study with the reason and vote for each.
Hiring impact
A court ruling or a lifted moratorium can put 2,951 MW back on the schedule at once. A court ruling in Joliet, a lifted moratorium at Shadowbox Studios or a water permit in Tooele Valley would put each of those sites back on the schedule. Contractors and commissioning firms that follow those dockets will see the restart first. The labor would come from the same metro pools shown on our construction labor gap page.
The cancelled projects that state a figure are small, 374 MW across 6 sites. The large cancellations, such as Prince William Digital Gateway and the Tract land in Buckeye, stated square footage or dollars and no MW, so their labor is not counted here.
Method and limits
- Projects: the 31 stalled or cancelled projects in our nine trackers as coded in the pushback study. Size figures come from the same public records as the tracker rows.
- Where a project states a range, the maximum is used (B+F Timpanogos, up to 30 MW). Shadowbox Studios' figure is the capacity it requested from Georgia Power.
- Workers per MW: 1.9 to 5.3, from Meta Richland Parish and the Abilene campus, the two named builds that publish both a peak workforce and a capacity. These are peak headcounts. Full-time job figures are on the job promises page.
- Square footage and investment are added up as stated and not converted to workers, since no published source gives a workers-per-square-foot figure for data centers.
- The strict count in the pushback study leaves out Cascade Locks (10 MW) and Stream Grove City (no MW). Under that count the stated total is 3,315 MW.
Questions
- How much data center capacity has local pushback blocked?
- In our October 2026 trackers, 9 of the 31 blocked projects state a capacity, and those 9 add up to 3,325 MW. 3 stalled projects hold 2,951 MW of it, and 6 cancelled projects hold 374 MW. The other 22 state no MW, so the real figure is higher.
- How many construction jobs did blocked data center projects remove?
- At the 1.9 to 5.3 workers per MW that named builds report, the 3,325 MW of stated capacity on blocked projects would have needed about 6,395 to 17,734 construction workers at peak. These are estimates of peak headcount. Full-time job figures are on the job promises page. The projects that publish a job figure of their own are on our job promises page.
Related
Northern Virginia shift
Where Northern Virginia's next sites are, and the blocked capacity megawatt counts miss.
Pushback study
Which tracked projects were stalled, denied or withdrawn, who stopped them and how.
Construction labor gap by metro
Tracked capacity under construction against the local construction workforce.
Hiring call
Book a hiring call and we'll talk through which roles your build needs and when to bring them on.

Czarina Tabayoyong
Founder and principal recruiter, Critical Path Hiring. Czarina recruits commissioning, MEP, power and critical facilities people for data center builds. She previously recruited cloud and data center architecture talent at AWS Professional Services, and PMO and project delivery talent for hyperscale data center campuses in Texas and Virginia.