Data center hiring runway

The vote that approves a data center and the first day it delivers capacity are, on the projects we track, about 21.5 months apart at the median. Groundbreaking to first capacity is about 12 months. This page lays out every tracked project with both dates, by state, and the targets that have already moved.

Czarina Tabayoyong, founder of Critical Path Hiring

By Czarina Tabayoyong, Founder, Critical Path Hiring. Former Amazon, AWS and Google recruiter.

Last reviewed · First published · Next update

Updated with the monthly tracker refresh.

Refresh alerts

One email each time this page is refreshed, with what changed.

Privacy policy

Findings

  • Approval to first stated target: median about 21.5 months across 9 projects, from 7 months (CloudBurst data center campus) to 34 to 45 months (Project Cardinal).
  • Texas runs short and Illinois runs long. The 3 Texas approvals in the set are county tax abatements or council votes that came after design, with a median of about 15.5 months to the first target. The 3 Illinois approvals are zoning and annexation votes at the start of the process, with a median of about 24 months.
  • Groundbreaking to first capacity: median about 12 months across 9 projects. Quarter-dated cases run from 10 months (DFW7 campus, Asphalt Drive) to 21 months (Dallas-Talty campus).
  • 4 tracked targets have already moved or paused: DC BLOX Atlanta West Hyperscale Campus, Cinco data center campus, DFW7 campus, Asphalt Drive, Microsoft Licking County campuses. The runways above are stated plans, so the real figures run longer.

Approval to target

  • Earliest the target allows
  • Latest the target allows
Months from public approval to first stated completion target9 tracked projects sorted shortest to longest: CloudBurst data center campus 7 months; Joule AI data center and energy campus 5 to 16 months; Cinco data center campus 10 to 21 months; CyrusOne data center west of Castroville 18 months; Devlin Technology Park 16 to 27 months; Project Vector 23 months; T5 Chicago IV (Cornerstone business park) 24 months; Amazon Marysville Innovation Park campus 22 to 33 months; Project Cardinal 34 to 45 months.02040CloudBurst data center campus: County tax abatement and development agreement approved 2026-04, target Q4 2026CloudBurst data center campusTexas7 monthsJoule AI data center and energy campus: County commission approved 2025-08, target 2026Joule AI data center and ener…Utah5 to 16 monthsCinco data center campus: City council and county commissioners approved 2025-03, target 2026Cinco data center campusTexas10 to 21 monthsCyrusOne data center west of Castroville: County tax abatement approved 2025-11, target June 2027CyrusOne data center west of …Texas18 monthsDevlin Technology Park: Rezoning upheld on appeal 2025-09, target 2027Devlin Technology ParkVirginia16 to 27 monthsProject Vector: City council approved 2025-12, target Q4 2027Project VectorIllinois23 monthsT5 Chicago IV (Cornerstone business park): Last village approval 2025-05, target Q2 2027T5 Chicago IV (Cornerstone bu…Illinois24 monthsAmazon Marysville Innovation Park campus: City council approved 30-year tax exemption 2025-03, target 2027Amazon Marysville Innovation …Ohio22 to 33 monthsProject Cardinal: City council final approval 2026-03, target 2029Project CardinalIllinois34 to 45 months
A year-only target shows as a range from January to December of that year. A quarter target counts as the middle month of the quarter.
ProjectMarketApprovalFirst stated targetMonths
CloudBurst data center campusInitial 50 MW phaseSan Antonio2026-04County tax abatement and development agreement approvedQ4 20267 months
Joule AI data center and energy campusCampus starts providing powerSalt Lake City2025-08County commission approved20265 to 16 months
Cinco data center campusFirst 60 MW phase; moved from Q4 2025San Antonio2025-03City council and county commissioners approved202610 to 21 months
CyrusOne data center west of CastrovilleSan Antonio2025-11County tax abatement approvedJune 202718 months
Devlin Technology ParkFirst approval came earlier; the appeal ruling is the last public decisionNorthern Virginia2025-09Rezoning upheld on appeal202716 to 27 months
Project VectorChicago2025-12City council approvedQ4 202723 months
T5 Chicago IV (Cornerstone business park)Building permit issued September 2026Chicago2025-05Last village approvalQ2 202724 months
Amazon Marysville Innovation Park campusColumbus2025-03City council approved 30-year tax exemption202722 to 33 months
Project CardinalChicago2026-03City council final approval202934 to 45 months

Groundbreaking to target

  • Earliest the target allows
  • Latest the target allows
Months from construction start to first stated completion target9 tracked projects sorted shortest to longest: Joule AI data center and energy campus 2 to 13 months; DFW7 campus, Asphalt Drive 10 months; Cinco data center campus 5 to 16 months; Stream San Antonio III campus 11 months; Cologix Lewis Center data center 12 months; Vantage Millersport campus 8 to 19 months; QTS Eagle Mountain campus (SLC1) 14 months; PowerCampus Dallas 20 months; Dallas-Talty campus 21 months.01020Joule AI data center and energy campus: Groundbreaking 2025-11, target 2026Joule AI data center and ener…Utah2 to 13 monthsDFW7 campus, Asphalt Drive: Construction started 2025-04, target Q1 2026DFW7 campus, Asphalt DriveTexas10 monthsCinco data center campus: Groundbreaking 2025-08, target 2026Cinco data center campusTexas5 to 16 monthsStream San Antonio III campus: Groundbreaking 2024-06, target Q2 2025Stream San Antonio III campusTexas11 monthsCologix Lewis Center data center: Work started 2025-11, target Q4 2026Cologix Lewis Center data cen…Ohio12 monthsVantage Millersport campus: Construction began 2026-05, target 2027Vantage Millersport campusOhio8 to 19 monthsQTS Eagle Mountain campus (SLC1): Work began 2025-09, target Q4 2026QTS Eagle Mountain campus (SL…Utah14 monthsPowerCampus Dallas: Work on first building began 2024-06, target Q1 2026PowerCampus DallasTexas20 monthsDallas-Talty campus: Site work expected (planned, not started) 2027-02, target Q4 2028Dallas-Talty campusTexas21 months
Dallas-Talty's start is a planned date. DFW7's target has passed with no completion report.
ProjectMarketConstruction startFirst stated targetMonths
Joule AI data center and energy campusSalt Lake City2025-11Groundbreaking20262 to 13 months
DFW7 campus, Asphalt DriveNo completion report found; a project database now shows 2027Dallas-Fort Worth2025-04Construction startedQ1 202610 months
Cinco data center campusFirst 60 MW phaseSan Antonio2025-08Groundbreaking20265 to 16 months
Stream San Antonio III campusFirst building, 40 MWSan Antonio2024-06GroundbreakingQ2 202511 months
Cologix Lewis Center data centerColumbus2025-11Work startedQ4 202612 months
Vantage Millersport campusColumbus2026-05Construction began20278 to 19 months
QTS Eagle Mountain campus (SLC1)Buildings 1 and 2 operationalSalt Lake City2025-09Work beganQ4 202614 months
PowerCampus DallasDallas-Fort Worth2024-06Work on first building beganQ1 202620 months
Dallas-Talty campusFirst customers move inDallas-Fort Worth2027-02Site work expected (planned, not started)Q4 202821 months

Slipped targets

ProjectMarketMilestoneStated beforeStated now
DC BLOX Atlanta West Hyperscale CampusAtlantaFirst 40 MW phase delivered20252026
Cinco data center campusSan AntonioFirst 60 MW phase onlineQ4 20252026
DFW7 campus, Asphalt DriveDallas-Fort WorthFirst phase completionQ1 20262027 in a project database; no completion reported
Microsoft Licking County campusesColumbusCampus plansThree campusesPaused April 2025; site work at one campus since February 2026

Hiring impact

Read the two medians together. Approval to first capacity is about 21.5 months and groundbreaking to first capacity about 12, so groundbreaking falls roughly 10 months after the vote on a typical tracked project. Construction hiring starts then. The commissioning window, the last two quarters before the target, opens about 6 months after groundbreaking. An owner who waits for the groundbreaking story to start a commissioning search has about half a year, and the collision page shows how many other sites open their window in the same quarter.

In Texas the public approval often comes late, after design, so a tax abatement vote is a signal that hiring is already under way. In Illinois the council vote comes first and the project has about two years to staff. The same headline, "county approves data center," means different things for a recruiter in Medina County and one in Kane County.

Method and limits

  • Projects: tracked projects under construction or approved with both a dated public decision or construction start in the public record and a stated first completion target on hiring windows by market. 9 qualify for the approval runway and 9 for the construction runway; two projects appear in both.
  • "Approval" is the last public vote or agreement we found: zoning, annexation, a conditional use permit or a tax abatement. Where a rezoning was appealed, the appeal ruling is used.
  • A quarter target counts as its middle month. A year-only target gives a January to December range and a June midpoint, and the medians use midpoints.
  • Targets are stated plans. Four have already moved, and the medians will lengthen as more do. First targets cover a first building or phase, not full buildout.
  • Small set: medians on 9 and 9 projects, and on 3 and 3 for the state comparison.

Download the data as CSV.

Questions

How long after approval does a data center open?
Across 9 tracked projects with a dated public approval and a stated completion target, the median is about 21.5 months from the approval to the first target. The 3 Texas projects run shorter at about 15.5 months, the 3 Illinois projects longer at about 24 months. These are stated targets, and several have already moved.
How long does data center construction take?
Among 9 tracked projects with a stated construction start and a first completion target, the median is about 12 months from groundbreaking to the first phase. The quarter-dated cases run from 10 months (DFW7 campus, Asphalt Drive) to 21 months (Dallas-Talty campus). First phases are usually one building or 40 to 70 MW, so this is the time to first capacity, not full buildout.

Hiring call

Book a hiring call and we'll talk through which roles your build needs and when to bring them on.

Czarina Tabayoyong, founder of Critical Path Hiring

Czarina Tabayoyong

Founder and principal recruiter, Critical Path Hiring. Czarina recruits commissioning, MEP, power and critical facilities people for data center builds. She previously recruited cloud and data center architecture talent at AWS Professional Services, and PMO and project delivery talent for hyperscale data center campuses in Texas and Virginia.

More about Czarina · LinkedIn