5 of the 15 Columbus data center projects we track sit in towns that voted for limits on November 3
None of the five projects under construction faced a vote. The measures landed on projects that had not started building.
Founder & Principal Recruiter · Published November 17, 2026
5 of the 15 Columbus data center projects we track sit in towns that voted for limits on November 3
Ohio voters decided 21 local data center measures on November 3, 2026, and sided against data centers in all 21. Four of the towns that voted hold projects on our Columbus tracker: Sunbury, Ashville, Grove City and Pataskala. Together they cover 5 of the 15 projects we track. The other 10, including all 5 under construction, are in places that had no measure on the ballot.
Projects
| Project | Town | Stage on our tracker | November 3 result |
|---|---|---|---|
| Aligned Pataskala data center, 200 MW | Pataskala | Stalled | Charter amendment banning data centers over 25 MW passed 5,418 to 1,941 |
| AWS Sunbury Business and Technology Park campus, $2 billion | Sunbury | Stalled | Charter amendment barring data centers above 25 MW passed with 78.64% |
| Sunbury annexed land rezoning, about 330 acres | Sunbury | Proposed | Same Sunbury charter amendment |
| EdgeConneX Ashville data centers, two buildings | Ashville | Cancelled | Voters repealed the village's agreement 1,468 to 330 |
| Stream Data Centers Grove City site | Grove City | Stalled | Issue 28 passed with 54.6%; projects over 20 MW, 50 acres or 500,000 gallons of water a day now need a public vote |
We matched each Ohio measure to the town of every project on our Columbus tracker. Vote counts are preliminary results as reported by local news.
Unaffected projects
The 5 projects under construction had no measure on the ballot in their towns: Vantage in Millersport, Cologix in Johnstown and Lewis Center, Meta in New Albany and Microsoft in Licking County. The 3 approved projects had none either: EdgeConneX in New Albany, Amazon in Marysville and Google's Lancaster expansion. Two proposed sites in Union County, Marysville South and the Jerome Township site, also had no vote.
Granville, in Licking County, passed a ban on data center construction. We track no project there.
Hiring
Crews on the 5 active builds keep working, so the commissioning and construction hiring tied to those sites is unchanged by the election.
The 5 projects in towns that voted had not started building. Four were already stalled or cancelled before November 3 by a moratorium, a council denial or a referendum petition, and the votes wrote those limits into town charters. Employers who planned to staff those sites should not count on them as a source of work or of released crews in 2027.
In Grove City, a project over 20 MW now has to win a public vote before it can proceed. Anyone planning a build there should add an election date to the schedule ahead of the first hire.
Method
The list of 21 Ohio measures and their results comes from Ballotpedia and the Gridsight vote tracker, both published November 6, 2026. Nationally, voters favored limits in 40 of 41 local data center measures. Project stages, sizes and vote counts come from our Columbus tracker, where each row links to its source. Results are preliminary until county boards certify them. A measure is matched to a project when the project sits inside the town that voted.
By market
Markets
Candidate supply and pay differ by metro. These pages cover the markets where this comes up most.
Questions
Questions
- Which Columbus-area data center projects were affected by the November 2026 election?
- Five projects on our Columbus tracker sit in towns that voted for limits on November 3, 2026: the Aligned project in Pataskala, the AWS campus and a rezoning request in Sunbury, the EdgeConneX project in Ashville and the Stream Data Centers site in Grove City.
- Did the Ohio data center votes stop any project under construction?
- No. None of the 5 Columbus-area projects under construction on our tracker is in a town that had a data center measure on the November 3, 2026 ballot.

Czarina Tabayoyong
Founder and principal recruiter, Critical Path Hiring. Czarina recruits commissioning, MEP, power and critical facilities people for data center builds. She previously recruited cloud and data center architecture talent at AWS Professional Services, and PMO and project delivery talent for hyperscale data center campuses in Texas and Virginia.
Hiring call
Book a hiring call and we'll talk through which roles your build needs and when to bring them on.