Stack's 1GW Stafford Technology Campus and Northern Virginia data center hiring
Up to 19 data centers on about 500 acres in Stafford County, with the first building topped out in May 2026, and the people it will need.
Founder & Principal Recruiter · Published October 23, 2026
Stack's 1GW Stafford Technology Campus and Northern Virginia data center hiring
Stack Infrastructure is building the Stafford Technology Campus, more than 1GW across up to 19 data centers on about 500 acres in Stafford County, Virginia. The first building topped out in May 2026. Each building will need commissioning, electrical, controls and operations people, and other Northern Virginia campuses are hiring the same people now.
The project
Stack announced the campus in a January 2025 press release. The Peterson Companies, the site's previous owner, won the rezoning in September 2024.
- Developer: Stack Infrastructure, which operates and develops 10 Northern Virginia campuses totaling more than 2.4GW
- Site: about 500 acres on the east side of US Route 1 at I-95, in the Falmouth area of Stafford County, across from Stafford Regional Airport
- Size: more than 1GW across up to 19 data centers in four sub-campuses
- Power: six 300MW substations supplied by Dominion Energy
- Cooling water: a reclaimed water system, known as purple pipe, so the campus does not draw on the county's drinking water
- Approvals: Stafford County supervisors approved a comprehensive plan amendment and rezoning for up to 23 buildings, 5.8 million sq ft and six substations
- Progress: in just over a year on the first building, project teams logged more than 425,000 hours, moved about three million cubic yards of earth and built 4,000 feet of retaining walls
- Jobs: Stack expects over 1,000 construction jobs at peak and hundreds of full-time jobs
- Dates: Peterson's earlier plan, reported by DatacenterDynamics, had the first phase live in 2027, and Baxtel's project listing shows phases running through 2036. Stack has not confirmed either date.
- Not announced yet: the tenant and the general contractor
Hiring order
Stack has not published a schedule for the later buildings. Campuses like this hire in a set order, and each search should be open before the milestone it depends on.
- Owner's team and design: owner's project managers and electrical and mechanical design leads, before design starts on each sub-campus
- Commissioning agent: hired during design, so it can review drawings and equipment submittals before anything is installed
- Construction: superintendents, MEP coordinators and managers, electrical superintendents for the substation and switchgear work, project controls and BIM/VDC coordinators, hired by the general contractor before it starts on site
- Commissioning: commissioning engineers, controls engineers and startup technicians before Level 3 testing
- Operations: chief engineers, critical facilities engineers and critical environment technicians during construction, so they watch Level 4 and Level 5 testing before they take over
The first building has topped out, so its commissioning and operations hiring comes next. With up to 19 data centers planned, the same hiring will repeat building by building for several years.
Competing campuses
EdgeCore announced in July 2024 that it bought 120 acres in Culpeper for a 1.4 million sq ft campus of 216MW to start, with room for 432MW. It expects power from Rappahannock Electric Cooperative in early 2028.
In Bristow, Amazon Data Services bought about 70% of the 270-acre Devlin Technology Park from Stanley Martin for $700 million in November 2025. The site is zoned for up to 3.5 million sq ft and three substations, and no construction has been reported there yet.
Stafford is at the south end of the market, so someone working in Ashburn is unlikely to want a daily drive there. The closest pool is Stafford, Spotsylvania and southern Prince William counties and Fredericksburg.
Employers
- Compare your commissioning and testing dates with Stafford's next buildings, and line up your commissioning people early if they overlap.
- Search by drive time to your site. For Stafford, start with Fredericksburg and the I-95 corridor before Loudoun County.
- Consider people from utilities, military facilities maintenance and industrial controls, with a planned first 90 days of training.
- Check your pay range against current commissioning pay before you post the role.
Candidates
- With up to 19 buildings planned in Stafford, commissioning, controls and critical facilities work there should run for several years.
- Ask any employer when the site will be energized, since that date sets when commissioning work peaks.
Sources
- STACK Infrastructure Announces Landmark 1+GW Stafford Technology Campus in Northern Virginia, STACK Infrastructure
- Peterson Cos. wins approval for huge data center campus in Stafford County, Washington Business Journal, reposted by The Peterson Companies
- First Building at Stack's 1GW Data Center Campus in Virginia Tops out in Stafford County, Baxtel
- Stack plans 1GW campus in Stafford County, Virginia, DatacenterDynamics
- Stack: Stafford Technology Campus (STC), Baxtel
- EdgeCore Acquires 120 Acres for New Culpeper Data Center Campus, TelecomTalk
- Amazon Buys Northern Virginia Data Center Site for Record $700 Million, Northern Virginia Magazine
By market
Markets
Candidate supply and pay differ by metro. These pages cover the markets where this comes up most.
Questions
Questions
- Where is the Stack Stafford Technology Campus?
- On about 500 acres on the east side of US Route 1 at I-95, in the Falmouth area of Stafford County, Virginia, across from Stafford Regional Airport.
- How big is the Stafford Technology Campus?
- More than 1GW across up to 19 data centers, powered by six 300MW substations supplied by Dominion Energy. The county's approval allows up to 23 buildings and 5.8 million sq ft.
- When will the Stafford Technology Campus hire?
- The first building topped out in May 2026, so its commissioning and operations hires come next. Stack has not published dates for the other buildings, and each one will hire its owner's team, construction, commissioning and operations people in turn.
Keep reading
Related work
Northern Virginia data center project tracker
Proposed, approved and active Northern Virginia campuses by county and stage, with a source for each.
Hiring timeline by build stage
Which roles to hire at each build stage and which milestone each search should be open before.
Northern Virginia data center hiring
Who is available in Northern Virginia, what they're paid and where they live.
Commissioning pay ranges
Posted pay ranges for commissioning engineers and managers, updated monthly.

Czarina Tabayoyong
Founder and principal recruiter, Critical Path Hiring. Czarina recruits commissioning, MEP, power and critical facilities people for data center builds. She previously recruited cloud and data center architecture talent at AWS Professional Services, and PMO and project delivery talent for hyperscale data center campuses in Texas and Virginia.
Hiring call
Book a hiring call and we'll talk through which roles your build needs and when to bring them on.