MEP and construction

MEP and construction is the second stage of a data center build. A general contractor puts up the building and the mechanical, electrical and plumbing (MEP) trades install the systems that power and cool the servers. It overlaps with power and site work at the start and with commissioning at the end.

Czarina Tabayoyong, founder of Critical Path Hiring

By Czarina Tabayoyong, Founder, Critical Path Hiring. Former Amazon, AWS and Google recruiter.

Last reviewed · First published

Reviewed as terms, pay and markets change.

MEP and constructionThree lanes feed into the building shell: electrical systems with switchgear, UPS, PDUs and busway; mechanical systems with chillers, cooling towers, CRAHs, pumps and piping; controls and low voltage with BMS, EPMS, fire alarm, security and fiber. The building leads to commissioning: L2 and L3 checks as each system is installed.Electrical: switchgear,UPS, PDUs, buswayMechanical: chillers, cooling towers,CRAHs, pumps and pipingControls and low voltage: BMS, EPMS,fire alarm, security, fiberBuilding shellCommissioning: L2 and L3checks as each systemis installed
Electrical: switchgear, UPS, PDUs, busway. Mechanical: chillers, cooling towers, CRAHs, pumps and piping. Controls and low voltage: BMS, EPMS, fire alarm, security, fiber. These trades feed into the building shell, then commissioning: L2 and L3 checks as each system is installed.

Work

The building shell

The general contractor (GC) runs the job. Crews pour foundations and slabs, erect the steel, and close in the roof and walls so the inside can be worked on in any weather. Many builds use prefabricated parts, such as electrical rooms built as skids or modules off site and set in place by crane.

Electrical systems

Electricians install the gear that takes power from the utility service to the servers: switchgear, transformers, uninterruptible power supplies (UPS) and their batteries, power distribution units (PDUs), busway and branch circuits. Most data centers build two separate power paths so a failure on one side does not drop the load.

Mechanical systems

Pipefitters and sheet metal workers install the cooling plant and the equipment that moves heat out of the data halls: chillers, cooling towers or dry coolers, pumps, piping and computer room air handlers (CRAHs). AI halls with liquid cooling add coolant distribution units (CDUs) and piping that runs to the racks.

Controls and low voltage

Controls contractors install the building management system (BMS) that runs the mechanical plant and the electrical power monitoring system (EPMS) that tracks every breaker and UPS. Low-voltage crews install fire alarm and suppression, security, cameras and the fiber and copper cabling.

People

General contractor

  • Project executives and project managers
  • Superintendents and MEP superintendents
  • MEP coordinators who resolve clashes between trades before install
  • Field engineers, schedulers and safety managers
  • Quality managers who track installation against the drawings

Trade contractors

  • Electrical foremen and journeyman electricians
  • Pipefitters, plumbers and sheet metal workers
  • Controls technicians and BMS programmers
  • Fire protection and low-voltage technicians

Owner side

  • Construction managers who represent the owner on site
  • Owner's MEP engineers who review submittals and change orders

Commissioning overlap

Commissioning agents are on site during construction. As each system is installed, they run level 2 checks on equipment delivery and installation and level 3 checks on startup of individual pieces of equipment. The issues they log here are what the GC and trades fix before level 4 functional testing.

Hiring impact

This stage needs the most people of any stage, and the trades are hired mostly by the GC and the trade contractors. Owners and GCs hire the leadership roles directly: MEP superintendents, MEP coordinators and quality managers who have delivered mission critical work. Candidates from commercial construction can move into this stage, but the ones who have built a data center can name the switchgear, UPS and cooling systems they installed and the commissioning levels they supported.

For when to open each search against the build schedule, see the hiring timeline by build stage.

Czarina Tabayoyong, founder of Critical Path Hiring

Czarina Tabayoyong

Founder and principal recruiter, Critical Path Hiring. Czarina recruits commissioning, MEP, power and critical facilities people for data center builds. She previously recruited cloud and data center architecture talent at AWS Professional Services, and PMO and project delivery talent for hyperscale data center campuses in Texas and Virginia.